GHMC Commissioner inspects development works in Serilingampally

Hyderabad: GHMC Commissioner RV Karnan inspected the work of the three-lane by-direction Shilpa Layout Flyover from Gachibowli to Kondapur.

During the inspection, the engineering officials said the work of BT and LED lights on the flyover was going on and the service road work would be completed in 15 days if the land acquisition process of about five properties was completed.

The Commissioner then ordered that it be completed by the end of this month and directed the Zonal Commissioner to complete the land acquisition process as soon as possible.

Serilingampally Zonal Commissioner Borkade Hemanth Sahadev Rao were also participated in inspection.